Sr. No |
Date |
Job Description |
Client Name |
Industry |
Remarks |
1 |
27-Sep-12 |
Repair of Sealing Seat Inside 13 5/8" 5000PSI Double Ram BOP |
Dewan Drilling Limited |
Petroleum Exploration Company |
Completed |
2 |
5-Oct-12 |
Refurbishment of Under Head Flange |
"CNPC Chuanqing Drilling Engineering Company Ltd. (CCDC)" |
Petroleum Exploration Company |
Completed |
3 |
23-Nov-12 |
Machining & Polishing of Gas Compressor BLP Liner |
General Electric |
Thermal Power Plant |
Completed |
4 |
8-Jan-13 |
Piston HE, CE and Piston Central Part |
General Electric |
Thermal Power Plant |
Completed |
5 |
2-Jan-13 |
Repair of PIN |
OGDCL |
Petroleum Exploration Company |
Completed |
6 |
810-Mar-13 |
Manufacturing of Ring |
NDC |
Defence |
Completed |
7 |
12-Apr-13 |
Ultrasonic testing , DPT and hardness testing |
Fauji Cement Company |
Cement Factory |
Completed |
8 |
20-May-13 |
Plasma Coating of Impeller & Wearing Rings |
Engro Fertilizer |
Fertilizer Plant |
Completed |
9 |
20-May-13 |
Coating & Machining of Shaft. |
Best Way Cement |
Cement Factory |
Completed |
10 |
20-May-13 |
Repairing of PINS |
OGDCL |
Petroleum Exploration Company |
Completed |
11 |
25-May-13 |
Plasma Coating of sleves |
Fatima fertilizer Company |
Fertilizer Plant |
Completed |
12 |
8-Jan-13 |
Coating,Machining and Grinding of Bearing Housing |
Bestway Cement MCL Hattar |
Cement Factory |
Completed |
13 |
26-Oct-13 |
Coating,Maching and Grinding of Roller Press Plantary gear Box |
Bestway Cement MCL Hattar |
Cement Factory |
Completed |
14 |
26-Oct-13 |
Rebuilding of Machining of Seal Set ring4 Set |
Bestway Cement MCL Hattar |
Cement Factory |
Completed |
15 |
10-Mar-13 |
Drepairing of Cement Mill Shaft |
DG Cement Kahirpure |
Cement Factory |
Completed |
16 |
12-May-13 |
NDT and Transportation Charges |
Fauji Cement Company |
Cement Factory |
Completed |
17 |
5-Jul-13 |
Reopairing of Exhaust Duct |
POL |
Petroleum Exploration Company |
Completed |
18 |
6-Sep-13 |
Machining of Rings |
NDC |
Defence |
Completed |
19 |
6-Sep-13 |
Machining of Rings |
NDC |
Defence |
Completed |
20 |
27-Nov-13 |
Mud Pump Moudle Repair |
OGDCL |
Petroleum Exploration Company |
Completed |
21 |
18-Mar-14 |
Machining of Bearings and Seal Rings |
Italtic Energy |
Thermal Power Plant |
Completed |
22 |
24-Mar-14 |
Gear Coupling and Module Repair |
OGDCL |
Petroleum Exploration Company |
Completed |
23 |
20-May-14 |
Repairing of Job |
OGDCL |
Petroleum Exploration Company |
Completed |
24 |
24-Jun-14 |
UT Services |
Velosi |
Testing Servics |
Completed |
25 |
21-Jul-14 |
Repair& refurbishment of MuD Pump Modules |
OGDCL |
Petroleum Exploration Company |
Completed |
26 |
15-Aug-14 |
Manufactruing of gear Coupling |
OGDCL |
Petroleum Exploration Company |
Completed |
27 |
1-Oct-14 |
Repairing of Turbine Jet |
POL |
Petroleum Exploration Company |
Completed |
28 |
13-Oct-14 |
ultrasonic testing Services |
Fauji Cement |
Cement Factory |
Completed |
29 |
31-Oct-14 |
Rebuilding and machining and gridning of shafts |
Rousch Power Plant |
Thermal Power Plant |
Completed |
30 |
31-Oct-14 |
Fabrication of QWD HuB for |
OGDCL RIG N2 |
Petroleum Exploration Company |
Completed |
31 |
24-Nov-14 |
Repairing of BFP Pump Shaft |
LALPIR Thermal Power |
Thermal Power Plant |
Completed |
32 |
26-Nov-14 |
Repairing and Refurbishment of Runner Casing of Shedo |
Shedo |
Hydrel power plant |
Completed |
33 |
6-Jan-15 |
Repairing and Refurbishment of Runner Casing of Shedo |
Shedo |
Hydrel power plant |
Completed |
34 |
7-Jan-15 |
UT Services Provided |
VELOSI Pakistan |
Testing Servics |
Completed |
35 |
12-Jan-15 |
Welding and Machining of Die Holer |
Asia Feeds Multan |
Poulty Feed Mill |
Completed |
36 |
12-Jan-15 |
Welding and machining of Mud Pump Module |
OGDCL |
Petroleum Exploration Company |
Completed |
37 |
21-Jan-15 |
Repairing of Die Holder Shafts |
Asia Feeds Multan |
Poulty Feed Mill |
Completed |
38 |
19-Feb-15 |
Rebuilding and machining drill |
KAPCO |
Thermal Power Plant |
Completed |
39 |
2-Mar-15 |
Rebuilding welding of rolls shell and manufacurting new bush |
Asia Feeds Multan |
Poulty Feed Mill |
Completed |
40 |
2-Mar-15 |
Repairing of Mud Pump Modules |
Pakistan Oil Field |
Petroleum Exploration Company |
Completed |
41 |
2-Mar-15 |
Repairing of Die Holder Shafts |
Asia Feeds Multan |
Poulty Feed Mill |
Completed |
42 |
03-Mar-15 |
Repairing of Die Holder Shafts |
Asia Feeds Multan |
Poulty Feed Mill |
Completed |
43 |
03-Mar-15 |
Repairing of Motor & Balancing |
Uch power bearings |
Thermal Power Plant |
Completed |
44 |
19-Mar-15 |
NDt Services at Site |
Fauji Cement |
Cement Factory |
Completed |
45 |
30-Mar-15 |
Manufacturing of Die Punch |
Prime Crate Advance |
Black Factory |
Completed |
46 |
4-Sep-15 |
Rebuiulding and gridning of Shaft Bell Mouth |
Rosuch Power |
Thermal Power Plant |
Completed |
47 |
8-Oct-15 |
UT Services |
Fauji Cement |
Cement Factory |
Completed |
48 |
21-Oct-15 |
Refurbishment of Module |
OGDCL Rig N 3 |
Petroleum Exploration Company |
Completed |
49 |
18-Nov-15 |
Refurbsihment of Runenr of shi shi |
PEDO |
Hydrel power plant |
Completed |
50 |
26-Nov-15 |
Repairing of Gear Housing |
FECTO Cement |
Cement Factory |
Completed |